Thanks for taking this on. The schedule for the North Commons opening is built, but my notes from the contractor never made it in. Three links are missing:
- Plumbing can start 2 working days after framing and electrical starts. The plumber works right behind the framers.
- Paint needs 2 working days to cure before the counters go in.
- Point of sale setup can't finish until 1 working day after the counters are installed. The terminals mount on them.
Once they're in, write down the critical path and the opening date in the status report. Set a baseline, too.
Forwarded from Quarrybend StoneworksYour counters ship 4 working days late. Fabrication is on schedule; the delivery is what moves.
Put that in, then tell me if we still open on time. Also, Mira is booked on two tasks the first week. Fix it without moving the opening.
Two questions for the report: what's the new opening date, and which task has the most slack? I want to know where we have room.
Quillfern Coffee is a made-up company, and everyone here is made up too. A practice scenario, built for you.